MRC Engineering were intially engaged by Story Contracting to undertake As-Built Design and CAD production following the collapse of Carillion and the loss of their Telecoms Contractor Opitlan. The scheme grew into MRC Engineering undertaking a new CCTV Gateline design for Platform 12.


Project Overview:

  • GRIP 5 Detailed Design for the Platform 5 CCTV Design

  • GRIP 7 As-Bults for the Full SISS Design on Edinburgh Waverley. This included the creation of new models based solely on PDF designs. This included, CCTV Relocations, CCTV Node Relocations and PA Enhancement


Project key deliverables / challenges:

  • Production of editable files in a condensed time scale to allow the completion of Edinburgh waverley and final handback to Network Rail

Client

Story Contracting

Scope

Station Information & Surveillance System

GRIP Stage

5, 7

Role & Responsibility

Telecoms Designer and CRE Design

Cadoxton Station

Cadoxton Station

Stevenage Station SISS

Stevenage Station SISS

Stevenage Turnback Ops

Stevenage Turnback Ops

Snow Hill Station - 3rd Entrance

Snow Hill Station - 3rd Entrance

Northumberland Line Railway

Northumberland Line Railway

Clachnaharry Swing Bridge

Clachnaharry Swing Bridge

bottom of page